Data centre power plans raise questions for regional climate targets
ProPublica reports that proposed power plants for two projects could emit up to 10 million tonnes of greenhouse gases a year combined. Permits and legal challenges remain unresolved.

Project Jupiter in Doña Ana County and a Meta data centre in El Paso are under construction, while a third facility is planned at Fort Bliss. ProPublica reports that the projects were not included in climate plans adopted by New Mexico and El Paso.
The report estimates that proposed power plants for Project Jupiter and Meta could emit up to 10 million tonnes of greenhouse gases annually combined. That is an estimate of potential emissions, not a measure of actual operating emissions. The Army has shared limited information about the Fort Bliss project, and its emissions are unclear.
The facilities could also release pollutants affecting local air quality. ProPublica reports that Texas and New Mexico regulators are assessing the projects separately, under different disclosure and review requirements.
Project Jupiter’s air permit remains under review. A hearing was delayed after opponents filed legal challenges and was later cleared to proceed. In Texas, El Paso Electric is awaiting state approval for the power plant planned to serve Meta’s facility.
Oracle and Meta say they plan mitigation measures, including clean energy projects elsewhere to offset emissions. Oracle has also said Project Jupiter’s emissions will be lower than those in its permit application and that it aims to reach net-zero greenhouse gas emissions by 2031. Plans and approvals may still change.